December deadlines

Seven December deadlines on Idaho power bills, data centers, and more

The Silver Spur session in Twin Falls on Dec. 9 and Idaho Power's cost of service comments on Dec. 14 lead the list. Here is what each one means and how to comment.

By Jeff A. Pierson · November 25, 2026

The Magic Valley: Seven public deadlines this December will help decide who pays for Idaho's growing demand for power, and whether a new gas pipeline can cross private land in Twin Falls County.

Every one of these cases takes comments from the public, and each can be filed online. How to comment is at the end of each item.


At a glance

Date Agency What Case or docket
Dec. 4 IPUC Idaho Power's Oregon sale IPC-E-26-21
Dec. 7 FERC CAISO large-load rules ER27-506-000
Dec. 9 FERC Silver Spur pipeline session, Twin Falls PF26-15-000
Dec. 9 CAISO Joint board meeting, online  
Dec. 14 IPUC Idaho Power cost of service IPC-E-26-07
Dec. 14 FERC Silver Spur written comments PF26-15-000
Dec. 16 FERC CAISO large-load rules, round two ER27-532-000
Dec. 16 IPUC Intermountain Gas winter stopgap INT-G-26-09

Dec. 9 in Twin Falls: a new gas pipeline

This is the date to circle in south-central Idaho. Northwest Pipeline, a Williams company, plans the Silver Spur gas pipeline: about 88 miles of new 24-inch pipe from the Ruby Pipeline in Elko County, Nev., north into Twin Falls County. It adds a new compressor station called Jackpot, a new unit at the Buhl station and two larger units at the Mountain Home station.

The line would carry about 275,000 dekatherms of natural gas a day into Idaho. Intermountain Gas has signed up for 100,000 of that. The company hasn't filed its formal application. FERC calls this stage pre-filing, and comments made now shape what FERC studies.

Scoping is the step where the public tells federal regulators what to study before they decide. FERC's notice lists topics such as water, wildlife, land use, noise and safety.

Landowners need to hear this part. FERC's notice says no one is required to sign an easement. But if FERC approves the project, the Natural Gas Act gives the company the right of eminent domain. If a landowner and the company can't agree, the company can go to court to condemn the land, and a judge sets the payment under state law.

Silver Spur also matters to every Idaho Power customer. Idaho Power testified it bought the last remaining firm capacity on the existing Northwest Pipeline in September 2024, and it bid for space on the new pipeline project to fuel its planned gas plants.


Dec. 14: Idaho Power's cost of service

Will you or large-load customers see a bigger increase in the cost of electricity?

Case IPC-E-26-07 picks the formula that splits the cost of the grid among homes, irrigators, businesses and industry. No rate change yet, but the method shapes every rate case after it.

Cost of service is the math that divides the cost of running the grid among groups of customers. Idaho Power opened the case in March and put four methods on the table. The company says big, concentrated growth, such as data centers, may change how those costs should be divided. If a data center doesn't cover the cost of serving it, other customers do. A technical hearing follows Jan. 19, 2027.


Dec. 16: Intermountain Gas's winter stopgap

An Intermountain Gas line crossed the Boise River on a wooden bridge in northwest Boise. The Ada County Highway District found the bridge unsafe and sped up its removal. On Oct. 14, gas stopped flowing through that line. The company says what's left can't carry winter demand, so it is feeding the area with liquefied natural gas, called LNG, from temporary equipment.

A contractor put the cost at about $4.4 million through Jan. 29. About $1.9 million is the gas itself, which goes through the yearly gas-cost adjustment on your bill. The other $2.5 million is the cost of running the stopgap. Intermountain wants to set that aside now and ask customers for it later, with carrying charges, which work like interest. A permanent line under the river is expected around March 2027.


Dec. 9: CAISO's boards meet online, and Idaho has a stake

Two boards meet together online that day: CAISO's Board of Governors and the Western Energy Markets Governing Body. That second board has the main say over the rules of the western power market Idaho Power has traded in every day since April 2018.

In March 2024, Idaho Power told CAISO it was leaning toward CAISO's next step, the Extended Day-Ahead Market, which schedules power a day ahead. It wants some issues settled first, including repayment for transmission revenue it could lose and protection against shifting costs onto other transmission customers. CAISO's market website still lists Idaho Power as leaning, not signed. Rocky Mountain Power, which serves eastern Idaho, has been in that market since it launched May 1. CAISO's planning calendar has a slot that day for utilities to report whether they're joining. If Idaho Power announces its choice in December, that's a likely place for it.

Control of these markets is shifting too. Authority over the rules is set to move from CAISO to a new regional group, the Regional Organization for Western Energy. Idaho has no seat on CAISO's board.


Dec. 7 and Dec. 16: CAISO's large-load rules at FERC

A large load is one customer that pulls a huge amount of power off the high-voltage grid, usually a data center. CAISO's proposal draws the line at 50 megawatts or more.

The rules exist because of FERC. On June 18, in dockets EL26-67 through EL26-72, the federal commission told all six regional grid operators it oversees that their rules for hooking up these customers may be unjust and unreasonable. FERC wanted a clear definition and a study process that doesn't drag. It also wanted protection, so other customers don't pay for grid upgrades built for one big user.

CAISO answered Nov. 16. Utility hookup studies would fit FERC's 60-to-90-day window. Big users would send hourly forecasts, and the utility could disconnect them remotely when the grid needs it. Each California utility that owns transmission lines would write its own deposit and cost rules to keep the bill off everyone else. CAISO filed twice that day. The second filing, marked "Resubmission," went in under a new docket number as a rate filing. The notice doesn't say what else changed.

These rules won't decide how a data center connects in Idaho Power territory. That stays with Idaho Power and the Idaho PUC. But Idaho Power trades in CAISO's real-time market and is leaning toward its day-ahead market too. More giant loads on the same market means more buyers chasing the same power. That can push up the prices Idaho Power pays, and those costs land on Idaho bills.


Dec. 4: Idaho Power's Oregon sale

Idaho Power wants to sell its entire Oregon service territory, about 20,000 customers in Malheur, Harney, Baker and Wallowa counties, to the Oregon Trail Electric Consumers Cooperative for $154 million. The company says the sale lets it put its money and crews into Idaho as demand climbs here, and that it will help keep Idaho rates affordable.


Jeff A. Pierson · jeffapierson.com · jeffapierson.substack.com

© 2026 Jeff A Pierson / Sharing and reposting permitted if the document remains unaltered and attribution is retained. Commercial use requires written permission.

Sources

  1. Federal Register notice of scoping, Silver Spur Project (PF26-15-000), Federal Energy Regulatory Commission, https://www.govinfo.gov/content/pkg/FR-2026-11-18/pdf/2026-23441.pdf, Nov. 18, 2026
  2. Combined Notice of Filings (ER27-506-000, CAISO large loads), Federal Energy Regulatory Commission, https://www.govinfo.gov/content/pkg/FR-2026-11-19/pdf/2026-23607.pdf, Nov. 19, 2026
  3. Combined Notice of Filings (ER27-506-001 and ER27-532-000), Federal Energy Regulatory Commission, https://www.govinfo.gov/content/pkg/FR-2026-11-23/pdf/2026-23765.pdf, Nov. 23, 2026
  4. Decision on Large Load Enhancements memo, California ISO, https://www.caiso.com/documents/decision-on-large-load-enhancements-memo-oct-2026.pdf, Oct. 2026
  5. Joint ISO Board of Governors and WEM Governing Body meeting, California ISO, https://www.caiso.com/meetings-events/calendar/joint-iso-board-of-governors-and-wem-governing-body-and-committees-meeting-12, Nov. 24, 2026
  6. WEM Governing Body planning calendar, California ISO, https://www.caiso.com/documents/wem-governing-body-planning-calendar-oct-2026.pdf, Oct. 13, 2026
  7. Idaho Power and Portland General Electric signal intent to join EDAM, California ISO, https://www.caiso.com/Documents/idaho-power-and-portland-general-electric-signal-intent-to-join-edam-iso-statement.pdf, March 21, 2024
  8. Notice of Schedule, Order No. 37170 (IPC-E-26-07), Idaho Public Utilities Commission, https://puc.idaho.gov/Fileroom/PublicFiles/ELEC/IPC/IPCE2607/OrdNotc/20260916Notice_of_Schedule_Order_No_37170.pdf, Sept. 16, 2026
  9. Notice of Petition, Order No. 36998 (IPC-E-26-07), Idaho Public Utilities Commission, https://puc.idaho.gov/Fileroom/PublicFiles/ELEC/IPC/IPCE2607/OrdNotc/20260413Notice_of_Petition_Order_No_36998.pdf, April 13, 2026
  10. Commission schedules customer hearing on Oregon territory sale (IPC-E-26-21), Idaho Public Utilities Commission, https://puc.idaho.gov/Fileroom/PublicFiles/Press/20260923Idaho%20Power%200923%20Release.pdf.pdf, Sept. 23, 2026
  11. Notice of Application and Modified Procedure, Order No. 37237 (INT-G-26-09), Idaho Public Utilities Commission, https://puc.idaho.gov/Fileroom/PublicFiles/GAS/INT/INTG2609/OrdNotc/20261119Notice_of_Application_Order_No_37237.pdf, Nov. 19, 2026
  12. Intermountain Gas signs agreement to secure natural gas capacity, Intermountain Gas Co., https://www.intgas.com, May 11, 2026
  13. 15 U.S.C. 717f, Natural Gas Act Section 7, Legal Information Institute, https://www.law.cornell.edu/uscode/text/15/717f, accessed Nov. 18, 2026
  14. PGE to join CAISO's EDAM, Idaho Power leaning towards participation, Clearing Up (NewsData), https://www.newsdata.com/clearing_up/supply_and_demand/pge-to-join-caisos-edam-idaho-power-leaning-towards-participation/article_8446dc7e-e86a-11ee-bd21-67dd98ded2a8.html, March 22, 2024
  15. Extended Day-Ahead Market (EDAM) participants, Western Energy Markets (California ISO), https://www.westernenergymarkets.com/extended-day-ahead-market-edam, accessed Nov. 24, 2026
  16. POWER Act Legislative Report (cites FERC Order Nos. EL26-67 to EL26-72, June 18, 2026), Oregon Public Utility Commission, Sept. 1, 2026